Key data

  • Client: Universitätsklinikum Rostock AöR
  • Planning: 2009 - 2010
  • Construction: 2010 - 2011
  • Contract price: 0.61 million euro
  • Scope of planning:

    General planning 
    Basic evaluation 
    Preliminary design 
    Design development 
    Approval design 
    Detailed design 
    Preparation and participation in contract award 
    Site supervision 
    Post-construction management and documentation

Competitions

Hybrid operating theatre, Rostock
Establishment of a hybrid operating theatre in an existing building

In the existing building of the Centre for Inner Medicine, Cardiology Department of the University Hospital, the existing facilities of the cardiac catheter measuring unit were redeveloped to establish a hybrid operating theatre. The room layout was adapted to satisfy user and hygiene requirements, and existing equipment was replaced by new medical technology. The first university hybrid operating theatre in the German state of Mecklenburg-Vorpommern makes it possible to perform complex operations, with interdisciplinary cooperation in the theatre.