Altenwerder and Neuhof substations, Schleswig-Holstein
Re-construction of switchgear facilities
Inros Lackner planned the construction of new switchgear facilities in Altenwerder and Neuhof, near Hamburg, to replace existing facilities. The substations are located to the south of Hamburg, and approximately 8 km apart. In Altenwerder, the work included nineteen 110 kV switchgear units. The existing plant was removed in phases, and the new facility constructed in three stages. Consultancy services relating to the modification of the central relay station, individual relay facilities and the network monitoring station were also provided. In Neuhof, the work involved four 110 kV switchgear units, which were connected to the existing facility.