Federal motorway A114, Berlin
The A114 federal motorway was completely renewed over a length of approx. 7 km between the junction with the A10, the Pankow motorway junction, and the Berlin urban network. In connection with the planning services required for this, various pipeline modification measures were carried out on existing facilities of Berliner Wasserbetriebe. Among other things, sewage pressure pipes were newly laid in open and trenchless construction methods. After the preliminary work, the actual construction work on the feeder began. Inros Lackner was also responsible for the investigation of the relief route, the planning of the traffic routing during the construction period and the renovation or redesign of the existing structures.
Client
Berliner WasserbetriebePlanning
2015-2019Realization
2017-2023Planning Scope
Project planning of civil engineering structures service phase 1-6, local construction supervision of the test drillings