Skip to main content

Bar ramp, Baden-Wuerttemberg

Creation of ecological continuity

In the course of implementing the European Water Framework Directive (WFD) in Baden-Württemberg, Inros Lackner was commissioned to create ecological passability for aquatic organisms at the Essel weir on the Murg in Gaggenau-Hörden. It is planned to dismantle the weir and the existing boulder ramp and to construct a bar ramp. In addition, the two guard rails upstream will be dismantled. The fall height of the Essel weir is approximately 1.35 m. Adjacent to the ramp, the bed of the Murg will be modelled. By modelling the watercourse, the ramp height is reduced to about 50 cm. This difference in height between the headwater and tailwater of the ramp is reduced with four basins. 

Client

Regierungspräsidium Karlsruhe

Planning

2018–2022

Realization

2022

Planning Scope

Service phase 1-9